Project Overview
Project at a Glance
| Project Name | Ras Ghareb Wind Farm |
| Installed Capacity | 262.5 MW |
| Location | Near Ras Ghareb, Gulf of Suez, Egypt |
| Project Model | Build-Own-Operate (BOO) |
| Offtaker | Egyptian Electricity Transmission Company (EETC) |
| ENGIE | Lead Developer — 40% |
| Toyota Tsusho + Eurus Energy | Equity Partners — 40% (jointly) |
| Orascom Construction | Civil & Electrical Works + Equity Partner — 20% |
Milestone Timeline
2017
Project Incorporation
14 December 2017
Financial Close
2018–2019
Construction (≈24 months)
2019
Commercial Operation Date (262.5 MW) — Ahead of Schedule
2017
Project Incorporation
14 December 2017
Financial Close
2018–2019
Construction (≈24 months)
2019
Commercial Operation Date (262.5 MW) — Ahead of Schedule
Project Location
Environmental & Social Commitment
Ras Ghareb Wind Energy is committed to operating the wind farm in full compliance with international environmental and social standards. Comprehensive assessments have been prepared in accordance with the requirements of international lenders, Egyptian national legislation, and the IFC Performance Standards.
All relevant disclosure documents — including the Environmental and Social Impact Assessment, Stakeholder Engagement Plan, and other supporting studies — are available on our Disclosures page.