The project will be built as an EPCM (Engineering, Procurement, and Construction Management) comprising two main packages :

Siemens Gamesa Renewable Energy provides wind turbines. There will be 125 turbines type G97, rated 2.1 MW with a hub height of 71 m
Orascom Construction provides Civil Works and Electrical Systems. This package includes (i) the turbines foundations, (ii) the site buildings and control room, (iii) the site roads, (iv) a network of 33kV cabling collecting the energy generated by the wind turbines, and (v) an on-site substation with step-up transformers to enable connection with the regional Suez Gulf 220kV overhead transmission line

The project also entered into a 15 year Long Term Service Agreement with Siemens Gamesa Renewable Energy.